Construction of 38 Staff Quarters for CE (NEZ) staff at Chandmari, Guwahati

  1. Type “A” 4 Nos. (4 storied): Plastering work completed. Finishing work is in progress.
  2. Type "B" 8 Nos. (4 storied): Plastering work completed.
  3. Type “B” 2 Nos. (D/S): Brick work completed.
  4. Type “C” 3 Nos. : Brick work completed.
  5. Type “C” 8 Nos. (4 stored): Inside plastering completed. Outside plastering is in progress.
  6. Type “D” 4 Nos. (4 stored): Plastering completed. Flooring in progress.
  7. Type “D” 6 Nos. (G + 3): Plastering completed.
  8. Type “E” 2 Nos. (Duplex): Flooring work in progress.
  9. Type “F” 1 No. (Duplex): Flooring work in progress.

Construction of Zonal office for AIR & DD, Guwahati

Centering and shuttering and steel reinforcement work of G / F slab in progress.


Construction of RSTI (T) Shillong

Work completed and ready for handling over.


Officers / Staff Available At (H/Q/Site) for Air Projects

Name Designation Phone No. E-mail
P. P. Pal DDG(E) 0361-2232707 deavm.cenez@air.org.in
Chandrika Prasad DDE 0361-2232936 chandrikadp@air.org.in
B. R. Mistry DDE 0361-2232540  
S. K. Deb DDE 0361-2232610  
K. K. Sharma DDE 0361-2232606 sharmakk22@yahoo.in
D. K. Sudame ADE 9435174621 dksudame@gmail.com
I.R. Sahani AE 9435413386 irsahani@gmail.com
S. Talukdar AE    
S. P. Singh AE    
Amit Paul SEA    
Nilmani Ghosh SEA    
P. K. Chakraborty EA    

ALL INDIA RADIO

DOORDARSHAN

RELATED WEBSITES

Contact Address

Dr. P. Kakoti's Building
G.S. Road, Ganeshguri
Guwahati 781006
Tel: +91-361-2232232
Fax: +91-361-2232232
Email: adgenez@nic.in

India Portal