Construction of 38 Staff Quarters for CE (NEZ) staff at Chandmari, Guwahati

  1. Type “A” 4 Nos. (4 storied): Plastering work completed. Finishing work is in progress.
  2. Type "B" 8 Nos. (4 storied): Plastering work completed.
  3. Type “B” 2 Nos. (D/S): Brick work completed.
  4. Type “C” 3 Nos. : Brick work completed.
  5. Type “C” 8 Nos. (4 stored): Inside plastering completed. Outside plastering is in progress.
  6. Type “D” 4 Nos. (4 stored): Plastering completed. Flooring in progress.
  7. Type “D” 6 Nos. (G + 3): Plastering completed.
  8. Type “E” 2 Nos. (Duplex): Flooring work in progress.
  9. Type “F” 1 No. (Duplex): Flooring work in progress.

Construction of Zonal office for AIR & DD, Guwahati

Centering and shuttering and steel reinforcement work of G / F slab in progress.

Construction of RSTI (T) Shillong

Work completed and ready for handling over.

Officers / Staff Available At (H/Q/Site) for Air Projects

Name Designation Phone No. E-mail
P. P. Pal DDG(E) 0361-2232707
Chandrika Prasad DDE 0361-2232936
B. R. Mistry DDE 0361-2232540  
S. K. Deb DDE 0361-2232610  
K. K. Sharma DDE 0361-2232606
D. K. Sudame ADE 9435174621
I.R. Sahani AE 9435413386
S. Talukdar AE    
S. P. Singh AE    
Amit Paul SEA    
Nilmani Ghosh SEA    
P. K. Chakraborty EA    




Contact Address

Dr. P. Kakoti's Building
G.S. Road, Ganeshguri
Guwahati 781006
Tel: +91-361-2232232
Fax: +91-361-2232232

India Portal